Recently, Tianjin Nangang LNG Cold Energy Comprehensive Utilization Demonstration Project, EPC contracted by CNCEC-TCC, successfully achieved intermediate handover, marking the project's official transition from the construction phase to the preparation for trial operation.

The project consists of a 10,000 Nm³/h air separation unit, gas turbine distributed energy system (including an 8 MW-class gas turbine generator, one 20 t/h medium-temperature and medium-pressure waste heat boiler, and one 25 t/h medium-temperature and medium-pressure gas-fired boiler), as well as supporting auxiliary and utility systems. During construction, faced with challenges such as a tight schedule, heavy tasks and changeable weather, the CNCEC-TCC project team took safety and quality as the foundation and schedule as the main line, made scientific arrangements and precise measures, focused on key tasks and consolidated responsibilities at all levels, successfully completing the intermediate handover. Its outstanding performance has won full recognition from the owner and the supervision team.
Moving forward, the project team will uphold the corporate spirit of "Strive in Unity, Pursue Excellence through Hard Work", go all out to support the owner in preparation for trial operation, strive to build a high-quality project, deliver a satisfactory result to the owner and the company, and contribute TCC’s strength to accelerating the group’s development into a world-class innovative engineering company.